AI infrastructure: what is announced, contracted and operating?
A project pipeline is only useful when each record says what its status means. Use these evidence questions before adding an announcement to a sales forecast.
| Stage | Evidence | Question |
|---|---|---|
| Announced | Dated announcement and accountable organisation | What is committed, and what remains an ambition? |
| Contracted | Identified parties and a disclosed award or scope | Who is authorised to procure our package? |
| Under construction | Dated construction evidence, site and applicable project details | Which packages are still open, and when are they needed? |
| Commissioning | Documented testing and acceptance status | What must pass before service begins? |
| Operating | Named operator and dated service/capacity evidence | Which capacity is live, and what does that measure mean? |
This is BARQ360's original analytical framework, not an official project certification or a claim that a specific development passed these checks.